Alan E Wilson - Construction Consultant - Adjudicator Arbitrator Engineer 

Construction Industry dispute resolution and project management. Legally qualified independent chartered engineer providing contract advice, adjudication and arbitration services.

Page selector    Introduction  |  Contract Advice  |  Payment Issues  |  Negotiation  |  Adjudication  |  Arbitration  |  Legislation  |  Contact |  Links 

On this page   

On this page    HGCR Act - Adjudication |  HGCR Act - Payment and Suspension |  Contracts (Rights of Third Parties) Act |  Scheme - Part I Adjudication |  Scheme - Part II Payment |  Late Payment of CommercialDebts

The Housing Grants, Construction and Regeneration Act 1996 - Adjudication

The general and adjudication provisions of The Housing Grants, Construction and Regeneration Act 1996 are as follows. © HMSO

  PART II
  CONSTRUCTION CONTRACTS
 
Introductory provisions
Construction contracts.     104. - (1) In this Part a "construction contract" means an agreement with a person for any of the following-
 
 
    (a) the carrying out of construction operations;
 
    (b) arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise;
 
    (c) providing his own labour, or the labour of others, for the carrying out of construction operations.
      (2) References in this Part to a construction contract include an agreement-
 
 
    (a) to do architectural, design, or surveying work, or
 
    (b) to provide advice on building, engineering, interior or exterior decoration or on the laying-out of landscape,
 in relation to construction operations.
      (3) References in this Part to a construction contract do not include a contract of employment (within the meaning of the Employment Rights Act 1996).
 
      (4) The Secretary of State may by order add to, amend or repeal any of the provisions of subsection (1), (2) or (3) as to the agreements which are construction contracts for the purposes of this Part or are to be taken or not to be taken as included in references to such contracts.
 
      No such order shall be made unless a draft of it has been laid before and approved by a resolution of each of House of Parliament.
 
      (5) Where an agreement relates to construction operations and other matters, this Part applies to it only so far as it relates to construction operations.
 
      An agreement relates to construction operations so far as it makes provision of any kind within subsection (1) or (2).
 
      (6) This Part applies only to construction contracts which-
 
 
    (a) are entered into after the commencement of this Part, and
 
    (b) relate to the carrying out of construction operations in England, Wales or Scotland.
      (7) This Part applies whether or not the law of England and Wales or Scotland is otherwise the applicable law in relation to the contract.
 
Meaning of "construction operations".     105. - (1) In this Part "construction operations" means, subject as follows, operations of any of the following descriptions-
 
 
    (a) construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings, or structures forming, or to form, part of the land (whether permanent or not);
 
    (b) construction, alteration, repair, maintenance, extension, demolition or dismantling of any works forming, or to form, part of the land, including (without prejudice to the foregoing) walls, roadworks, power-lines, telecommunication apparatus, aircraft runways, docks and harbours, railways, inland waterways, pipe-lines, reservoirs, water-mains, wells, sewers, industrial plant and installations for purposes of land drainage, coast protection or defence;
 
    (c) installation in any building or structure of fittings forming part of the land, including (without prejudice to the foregoing) systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or security or communications systems;
 
    (d) external or internal cleaning of buildings and structures, so far as carried out in the course of their construction, alteration, repair, extension or restoration;
 
    (e) operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works;
 
    (f) painting or decorating the internal or external surfaces of any building or structure.
      (2) The following operations are not construction operations within the meaning of this Part-
 
 
    (a) drilling for, or extraction of, oil or natural gas;
 
    (b) extraction (whether by underground or surface working) of minerals; tunnelling or boring, or construction of underground works, for this purpose;
 
    (c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is-
 
      (i) nuclear processing, power generation, or water or effluent treatment, or
 
      (ii) the production, transmission, processing or bulk storage (other than warehousing) of chemicals, pharmaceuticals, oil, gas, steel or food and drink;
 
    (d) manufacture or delivery to site of-
 
      (i) building or engineering components or equipment,
 
      (ii) materials, plant or machinery, or
 
      (iii) components for systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or for security or communications systems,
  except under a contract which also provides for their installation;
 
    (e) the making, installation and repair of artistic works, being sculptures, murals and other works which are wholly artistic in nature.
      (3) The Secretary of State may by order add to, amend or repeal any of the provisions of subsection (1) or (2) as to the operations and work to be treated as construction operations for the purposes of this Part.
 
      (4) No such order shall be made unless a draft of it has been laid before and approved by a resolution of each House of Parliament.
 
Provisions not applicable to contract with residential occupier.     106. - (1) This Part does not apply-
 
 
    (a) to a construction contract with a residential occupier (see below), or
 
    (b) to any other description of construction contract excluded from the operation of this Part by order of the Secretary of State.
      (2) A construction contract with a residential occupier means a construction contract which principally relates to operations on a dwelling which one of the parties to the contract occupies, or intends to occupy, as his residence.
 
      In this subsection "dwelling" means a dwelling-house or a flat; and for this purpose-
 
 
    "dwelling-house" does not include a building containing a flat; and
 
    "flat" means separate and self-contained premises constructed or adapted for use for residential purposes and forming part of a building from some other part of which the premises are divided horizontally.
      (3) The Secretary of State may by order amend subsection (2).
 
      (4) No order under this section shall be made unless a draft of it has been laid before and approved by a resolution of each House of Parliament.
 
Provisions applicable only to agreements in writing.     107. - (1) The provisions of this Part apply only where the construction contract is in writing, and any other agreement between the parties as to any matter is effective for the purposes of this Part only if in writing.
 
      The expressions"agreement", "agree" and "agreed" shall be construed accordingly.
 
      (2) There is an agreement in writing-
 
 
    (a) if the agreement is made in writing (whether or not it is signed by the parties),
 
    (b) if the agreement is made by exchange of communications in writing, or
 
    (c) if the agreement is evidenced in writing.
      (3) Where parties agree otherwise than in writing by reference to terms which are in writing, they make an agreement in writing.
 
      (4) An agreement is evidenced in writing if an agreement made otherwise than in writing is recorded by one of the parties, or by a third party, with the authority of the parties to the agreement.
 
      (5) An exchange of written submissions in adjudication proceedings, or in arbitral or legal proceedings in which the existence of an agreement otherwise than in writing is alleged by one party against another party and not denied by the other party in his response constitutes as between those parties an agreement in writing to the effect alleged.
 
      (6) References in this Part to anything being written or in writing include its being recorded by any means.
 
 
Adjudication
Right to refer disputes to adjudication.     108. - (1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section.
 
      For this purpose "dispute" includes any difference.
 
      (2) The contract shall-
 
 
    (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication;
 
    (b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice;
 
    (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred;
 
    (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred;
 
    (e) impose a duty on the adjudicator to act impartially; and
 
    (f) enable the adjudicator to take the initiative in ascertaining the facts and the law.
      (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
 
      The parties may agree to accept the decision of the adjudicator as finally determining the dispute.
 
      (4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability.
 
      (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.
 
      (6) For England and Wales, the Scheme may apply the provisions of the Arbitration Act 1996 with such adaptations and modifications as appear to the Minister making the scheme to be appropriate.
 
      For Scotland, the Scheme may include provision conferring powers on courts in relation to adjudication and provision relating to the enforcement of the adjudicator's decision.
 

top of page


The Housing Grants, Construction and Regeneration Act 1996 - Payment

The payment provisions of The Housing Grants, Construction and Regeneration Act 1996 are as follows. © HMSO

 
Payment
Entitlement to stage payments.     109. - (1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless-
 
 
    (a) it is specified in the contract that the duration of the work is to be less than 45 days, or
 
    (b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
      (2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
 
      (3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
 
      (4) References in the following sections to a payment under the contract include a payment by virtue of this section.
 
Dates for payment.     110. - (1) Every construction contract shall-
 
 
    (a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
 
    (b) provide for a final date for payment in relation to any sum which becomes due.
     
      The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
      (2) Every construction contract shall provide for the giving of notice by a party not later than five days after the date on which a payment becomes due from him under the contract, or would have become due if-
 
 
    (a) the other party had carried out his obligations under the contract, and
 
    (b) no set-off or abatement was permitted by reference to any sum claimed to be due under one or more other contracts,
  specifying the amount (if any) of the payment made or proposed to be made, and the basis on which that amount was calculated.
      (3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) or (2), the relevant provisions of the Scheme for Construction Contracts apply.
 
Notice of intention to withhold payment.     111. - (1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment.
 
      The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section.
 
      (2) To be effective such a notice must specify-
 
 
    (a) the amount proposed to be withheld and the ground for withholding payment, or
 
    (b) if there is more than one ground, each ground and the amount attributable to it,
  and must be given not later than the prescribed period before the final date for payment.
      (3) The parties are free to agree what that prescribed period is to be.
 
      In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts.
 
      (4) Where an effective notice of intention to withhold payment is given, but on the matter being referred to adjudication it is decided that the whole or part of the amount should be paid, the decision shall be construed as requiring payment not later than-
 
 
    (a) seven days from the date of the decision, or
 
    (b) the date which apart from the notice would have been the final date for payment,
  whichever is the later.
Right to suspend performance for non-payment.     112. - (1) Where a sum due under a construction contract is not paid in full by the final date for payment and no effective notice to withhold payment has been given, the person to whom the sum is due has the right (without prejudice to any other right or remedy) to suspend performance of his obligations under the contract to the party by whom payment ought to have been made ("the party in default").
 
      (2) The right may not be exercised without first giving to the party in default at least seven days' notice of intention to suspend performance, stating the ground or grounds on which it is intended to suspend performance.
 
      (3) The right to suspend performance ceases when the party in default makes payment in full of the amount due.
 
      (4) Any period during which performance is suspended in pursuance of the right conferred by this section shall be disregarded in computing for the purposes of any contractual time limit the time taken, by the party exercising the right or by a third party, to complete any work directly or indirectly affected by the exercise of the right.
 
      Where the contractual time limit is set by reference to a date rather than a period, the date shall be adjusted accordingly.
 
Prohibition of conditional payment provisions.     113. - (1) A provision making payment under a construction contract conditional on the payer receiving payment from a third person is ineffective, unless that third person, or any other person payment by whom is under the contract (directly or indirectly) a condition of payment by that third person, is insolvent.
 
      (2) For the purposes of this section a company becomes insolvent-
 
 
    (a) on the making of an administration order against it under Part II of the Insolvency Act 1986,
 
    (b) on the appointment of an administrative receiver or a receiver or manager of its property under Chapter I of Part III of that Act, or the appointment of a receiver under Chapter II of that Part,
 
    (c) on the passing of a resolution for voluntary winding-up without a declaration of solvency under section 89 of that Act, or
 
    (d) on the making of a winding-up order under Part IV or V of that Act.
      (3) For the purposes of this section a partnership becomes insolvent-
 
 
    (a) on the making of a winding-up order against it under any provision of the Insolvency Act 1986 as applied by an order under section 420 of that Act, or
 
    (b) when sequestration is awarded on the estate of the partnership under section 12 of the Bankruptcy (Scotland) Act 1985 or the partnership grants a trust deed for its creditors.
      (4) For the purposes of this section an individual becomes insolvent-
 
 
    (a) on the making of a bankruptcy order against him under Part IX of the Insolvency Act 1986, or
 
    (b) on the sequestration of his estate under the Bankruptcy (Scotland) Act 1985 or when he grants a trust deed for his creditors.
      (5) A company, partnership or individual shall also be treated as insolvent on the occurrence of any event corresponding to those specified in subsection (2), (3) or (4) under the law of Northern Ireland or of a country outside the United Kingdom.
 
      (6) Where a provision is rendered ineffective by subsection (1), the parties are free to agree other terms for payment.
 
      In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
 
 
Supplementary provisions
The Scheme for Construction Contracts.     114. - (1) The Minister shall by regulations make a scheme ("the Scheme for Construction Contracts") containing provision about the matters referred to in the preceding provisions of this Part.
 
      (2) Before making any regulations under this section the Minister shall consult such persons as he thinks fit.
 
      (3) In this section "the Minister" means-
 
 
    (a) for England and Wales, the Secretary of State, and
 
    (b) for Scotland, the Lord Advocate.
      (4) Where any provisions of the Scheme for Construction Contracts apply by virtue of this Part in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned.
 
      (5) Regulations under this section shall not be made unless a draft of them has been approved by resolution of each House of Parliament.
 
Service of notices, &c.     115. - (1) The parties are free to agree on the manner of service of any notice or other document required or authorised to be served in pursuance of the construction contract or for any of the purposes of this Part.
 
      (2) If or to the extent that there is no such agreement the following provisions apply.
 
      (3) A notice or other document may be served on a person by any effective means.
 
      (4) If a notice or other document is addressed, pre-paid and delivered by post-
 
 
    (a) to the addressee's last known principal residence or, if he is or has been carrying on a trade, profession or business, his last known principal business address, or
 
    (b) where the addressee is a body corporate, to the body's registered or principal office,
  it shall be treated as effectively served.
      (5) This section does not apply to the service of documents for the purposes of legal proceedings, for which provision is made by rules of court.
 
      (6) References in this Part to a notice or other document include any form of communication in writing and references to service shall be construed accordingly.
 
Reckoning periods of time.     116. - (1) For the purposes of this Part periods of time shall be reckoned as follows.
 
      (2) Where an act is required to be done within a specified period after or from a specified date, the period begins immediately after that date.
 
      (3) Where the period would include Christmas Day, Good Friday or a day which under the Banking and Financial Dealings Act 1971 is a bank holiday in England and Wales or, as the case may be, in Scotland, that day shall be excluded.
 
Crown application.     117. - (1) This Part applies to a construction contract entered into by or on behalf of the Crown otherwise than by or on behalf of Her Majesty in her private capacity.
 
      (2) This Part applies to a construction contract entered into on behalf of the Duchy of Cornwall notwithstanding any Crown interest.
 
      (3) Where a construction contract is entered into by or on behalf of Her Majesty in right of the Duchy of Lancaster, Her Majesty shall be represented, for the purposes of any adjudication or other proceedings arising out of the contract by virtue of this Part, by the Chancellor of the Duchy or such person as he may appoint.
 
      (4) Where a construction contract is entered into on behalf of the Duchy of Cornwall, the Duke of Cornwall or the possessor for the time being of the Duchy shall be represented, for the purposes of any adjudication or other proceedings arising out of the contract by virtue of this Part, by such person as he may appoint.
 

top of page


The Scheme for Construction Contracts 1998 - Part I Adjudication

The Scheme for Construction Contracts 1998 Part I relating to Adjudication is as follows. © HMSO

1998 No. 649


CONSTRUCTION, ENGLAND AND WALES

The Scheme for Construction Contracts (England and Wales) Regulations 1998

  Made 6th March 1998 
  Coming into force 1st May 1998 

The Secretary of State, in exercise of the powers conferred on him by sections 108(6), 114 and 146(1) and (2) of the Housing Grants, Construction and Regeneration Act 1996[1], and of all other powers enabling him in that behalf, having consulted such persons as he thinks fit, and draft Regulations having been approved by both Houses of Parliament, hereby makes the following Regulations:

Citation, commencement, extent and interpretation
     1.  - (1) These Regulations may be cited as the Scheme for Construction Contracts (England and Wales) Regulations 1998 and shall come into force at the end of the period of 8 weeks begining with the day on which they are made (the "commencement date").

    (2) These Regulations shall extend only to England and Wales.

    (3) In these Regulations, "the Act" means the Housing Grants, Construction and Regeneration Act 1996.

The Scheme for Construction Contracts
     2. Where a construction contract does not comply with the requirements of section 108(1) to (4) of the Act, the adjudication provisions in Part I of the Schedule to these Regulations shall apply.

     3. Where - 

the relevant provisions in Part II of the Schedule to these Regulations shall apply.

     4. The provisions in the Schedule to these Regulations shall be the Scheme for Construction Contracts for the purposes of section 114 of the Act.



Signed by authority of the Secretary of State


Nick Raynsford
Parliamentary Under-Secretary of State, Department of the Environment, Transport and the Regions

6th March 1998



SCHEDULE

Regulations 2, 3 and 4


THE SCHEME FOR CONSTRUCTION CONTRACTS




PART I - 

ADJUDICATION

Notice of Intention to seek Adjudication
     1.  - (1) Any party to a construction contract (the "referring party") may give written notice (the "notice of adjudication") of his intention to refer any dispute arising under the contract, to adjudication.

    (2) The notice of adjudication shall be given to every other party to the contract.

    (3) The notice of adjudication shall set out briefly - 

     2.  - (1) Following the giving of a notice of adjudication and subject to any agreement between the parties to the dispute as to who shall act as adjudicator - 

    (2) A person requested to act as adjudicator in accordance with the provisions of paragraph (1) shall indicate whether or not he is willing to act within two days of receiving the request.

    (3) In this paragraph, and in paragraphs 5 and 6 below, an "adjudicator nominating body" shall mean a body (not being a natural person and not being a party to the dispute) which holds itself out publicly as a body which will select an adjudicator when requested to do so by a referring party.

     3. The request referred to in paragraphs 2, 5 and 6 shall be accompanied by a copy of the notice of adjudication.

     4. Any person requested or selected to act as adjudicator in accordance with paragraphs 2, 5 or 6 shall be a natural person acting in his personal capacity. A person requested or selected to act as an adjudicator shall not be an employee of any of the parties to the dispute and shall declare any interest, financial or otherwise, in any matter relating to the dispute.

     5.  - (1) The nominating body referred to in paragraphs 2(1)(b) and 6(1)(b) or the adjudicator nominating body referred to in paragraphs 2(1)(c), 5(2)(b) and 6(1)(c) must communicate the selection of an adjudicator to the referring party within five days of receiving a request to do so.

    (2) Where the nominating body or the adjudicator nominating body fails to comply with paragraph (1), the referring party may - 

    (3) The person requested to act as adjudicator in accordance with the provisions of paragraphs (1) or (2) shall indicate whether or not he is willing to act within two days of receiving the request.

     6.  - (1) Where an adjudicator who is named in the contract indicates to the parties that he is unable or unwilling to act, or where he fails to respond in accordance with paragraph 2(2), the referring party may - 

    (2) The person requested to act in accordance with the provisions of paragraph (1) shall indicate whether or not he is willing to act within two days of receiving the request.

     7.  - (1) Where an adjudicator has been selected in accordance with paragraphs 2, 5 or 6, the referring party shall, not later than seven days from the date of the notice of adjudication, refer the dispute in writing (the "referral notice") to the adjudicator.

    (2) A referral notice shall be accompanied by copies of, or relevant extracts from, the construction contract and such other documents as the referring party intends to rely upon.

    (3) The referring party shall, at the same time as he sends to the adjudicator the documents referred to in paragraphs (1) and (2), send copies of those documents to every other party to the dispute.

     8.  - (1) The adjudicator may, with the consent of all the parties to those disputes, adjudicate at the same time on more than one dispute under the same contract.

    (2) The adjudicator may, with the consent of all the parties to those disputes, adjudicate at the same time on related disputes under different contracts, whether or not one or more of those parties is a party to those disputes.

    (3) All the parties in paragraphs (1) and (2) respectively may agree to extend the period within which the adjudicator may reach a decision in relation to all or any of these disputes.

    (4) Where an adjudicator ceases to act because a dispute is to be adjudicated on by another person in terms of this paragraph, that adjudicator's fees and expenses shall be determined in accordance with paragraph 25.

     9.  - (1) An adjudicator may resign at any time on giving notice in writing to the parties to the dispute.

    (2) An adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication.

    (3) Where an adjudicator ceases to act under paragraph 9(1) - 

    (4) Where an adjudicator resigns in the circumstances referred to in paragraph (2), or where a dispute varies significantly from the dispute referred to him in the referral notice and for that reason he is not competent to decide it, the adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses reasonably incurred by him. The parties shall be jointly and severally liable for any sum which remains outstanding following the making of any determination on how the payment shall be apportioned.

     10. Where any party to the dispute objects to the appointment of a particular person as adjudicator, that objection shall not invalidate the adjudicator's appointment nor any decision he may reach in accordance with paragraph 20.

     11.  - (1) The parties to a dispute may at any time agree to revoke the appointment of the adjudicator. The adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses incurred by him. The parties shall be jointly and severally liable for any sum which remains outstanding following the making of any determination on how the payment shall be apportioned.

    (2) Where the revocation of the appointment of the adjudicator is due to the default or misconduct of the adjudicator, the parties shall not be liable to pay the adjudicator's fees and expenses.

Powers of the adjudicator
     12. The adjudicator shall - 

     13. The adjudicator may take the initiative in ascertaining the facts and the law necessary to determine the dispute, and shall decide on the procedure to be followed in the adjudication. In particular he may - 

     14. The parties shall comply with any request or direction of the adjudicator in relation to the adjudication.

     15. If, without showing sufficient cause, a party fails to comply with any request, direction or timetable of the adjudicator made in accordance with his powers, fails to produce any document or written statement requested by the adjudicator, or in any other way fails to comply with a requirement under these provisions relating to the adjudication, the adjudicator may - 

     16.  - (1) Subject to any agreement between the parties to the contrary, and to the terms of paragraph (2) below, any party to the dispute may be assisted by, or represented by, such advisers or representatives (whether legally qualified or not) as he considers appropriate.

    (2) Where the adjudicator is considering oral evidence or representations, a party to the dispute may not be represented by more than one person, unless the adjudicator gives directions to the contrary.

     17. The adjudicator shall consider any relevant information submitted to him by any of the parties to the dispute and shall make available to them any information to be taken into account in reaching his decision.

18.The adjudicator and any party to the dispute shall not disclose to any other person any information or document provided to him in connection with the adjudication which the party supplying it has indicated is to be treated as confidential, except to the extent that it is necessary for the purposes of, or in connection with, the adjudication.

     19.  - (1) The adjudicator shall reach his decision not later than - 

    (2) Where the adjudicator fails, for any reason, to reach his decision in accordance with paragraph (1)

    (3) As soon as possible after he has reached a decision, the adjudicator shall deliver a copy of that decision to each of the parties to the contract.

Adjudicator's decision
     20. The adjudicator shall decide the matters in dispute. He may take into account any other matters which the parties to the dispute agree should be within the scope of the adjudication or which are matters under the contract which he considers are necessarily connected with the dispute. In particular, he may - 

     21. In the absence of any directions by the adjudicator relating to the time for performance of his decision, the parties shall be required to comply with any decision of the adjudicator immediately on delivery of the decision to the parties in accordance with this paragraph.

     22. If requested by one of the parties to the dispute, the adjudicator shall provide reasons for his decision.

Effects of the decision
     23.  - (1) In his decision, the adjudicator may, if he thinks fit, order any of the parties to comply peremptorily with his decision or any part of it.

    (2) The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.

     24. Section 42 of the Arbitration Act 1996 shall apply to this Scheme subject to the following modifications - 

     25. The adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses reasonably incurred by him. The parties shall be jointly and severally liable for any sum which remains outstanding following the making of any determination on how the payment shall be apportioned.

     26. The adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and any employee or agent of the adjudicator shall be similarly protected from liability.

top of page


The Scheme for Construction Contracts 1998 - Part II Payment

The payment provisions of the Scheme for Construction Contracts 1998 are as follows. © HMSO

PART II - 

PAYMENT

Entitlement to and amount of stage payments
     1. Where the parties to a relevant construction contract fail to agree - 

    (a) the amount of any instalment or stage or periodic payment for any work under the contract, or

    (b) the intervals at which, or circumstances in which, such payments become due under that contract, or

    (c) both of the matters mentioned in sub-paragraphs (a) and (b) above,

the relevant provisions of paragraphs 2 to 4 below shall apply.

     2.  - (1) The amount of any payment by way of instalments or stage or periodic payments in respect of a relevant period shall be the difference between the amount determined in accordance with sub-paragraph (2) and the amount determined in accordance with sub-paragraph (3).

    (2) The aggregate of the following amounts - 

    (a) an amount equal to the value of any work performed in accordance with the relevant construction contract during the period from the commencement of the contract to the end of the relevant period (excluding any amount calculated in accordance with sub-paragraph (b)),

    (b) where the contract provides for payment for materials, an amount equal to the value of any materials manufactured on site or brought onto site for the purposes of the works during the period from the commencement of the contract to the end of the relevant period, and

    (c) any other amount or sum which the contract specifies shall be payable during or in respect of the period from the commencement of the contract to the end of the relevant period.

    (3) The aggregate of any sums which have been paid or are due for payment by way of instalments, stage or periodic payments during the period from the commencement of the contract to the end of the relevant period.

    (4) An amount calculated in accordance with this paragraph shall not exceed the difference between - 

    (a) the contract price, and

    (b) the aggregate of the instalments or stage or periodic payments which have become due.

Dates for payment
     3. Where the parties to a construction contract fail to provide an adequate mechanism for determining either what payments become due under the contract, or when they become due for payment, or both, the relevant provisions of paragraphs 4 to 7 shall apply.

     4. Any payment of a kind mentioned in paragraph 2 above shall become due on whichever of the following dates occurs later - 

    (a) the expiry of 7 days following the relevant period mentioned in paragraph 2(1) above, or

    (b) the making of a claim by the payee.

     5. The final payment payable under a relevant construction contract, namely the payment of an amount equal to the difference (if any) between - 

    (a) the contract price, and

    (b) the aggregate of any instalment or stage or periodic payments which have become due under the contract,

shall become due on the expiry of - 

    (a) 30 days following completion of the work, or

    (b) the making of a claim by the payee,

whichever is the later.

     6. Payment of the contract price under a construction contract (not being a relevant construction contract) shall become due on

    (a) the expiry of 30 days following the completion of the work, or

    (b) the making of a claim by the payee,

whichever is the later.

     7. Any other payment under a construction contract shall become due

    (a) on the expiry of 7 days following the completion of the work to which the payment relates, or

    (b) the making of a claim by the payee,

whichever is the later.

Final date for payment
     8.  - (1) Where the parties to a construction contract fail to provide a final date for payment in relation to any sum which becomes due under a construction contract, the provisions of this paragraph shall apply.

    (2) The final date for the making of any payment of a kind mentioned in paragraphs 2, 5, 6 or 7, shall be 17 days from the date that payment becomes due.

Notice specifying amount of payment
     9. A party to a construction contract shall, not later than 5 days after the date on which any payment - 

    (a) becomes due from him, or

    (b) would have become due, if - 

      (i) the other party had carried out his obligations under the contract, and

      (ii) no set-off or abatement was permitted by reference to any sum claimed to be due under one or more other contracts,

    give notice to the other party to the contract specifying the amount (if any) of the payment he has made or proposes to make, specifying to what the payment relates and the basis on which that amount is calculated.

Notice of intention to withhold payment
     10. Any notice of intention to withhold payment mentioned in section 111 of the Act shall be given not later than the prescribed period, which is to say not later than 7 days before the final date for payment determined either in accordance with the construction contract, or where no such provision is made in the contract, in accordance with paragraph 8 above.

Prohibition of conditional payment provisions
     11. Where a provision making payment under a construction contract conditional on the payer receiving payment from a third person is ineffective as mentioned in section 113 of the Act, and the parties have not agreed other terms for payment, the relevant provisions of - 

    (a) paragraphs 2, 4, 5, 7, 8, 9 and 10 shall apply in the case of a relevant construction contract, and

    (b) paragraphs 6, 7, 8, 9 and 10 shall apply in the case of any other construction contract.

Interpretation
     12. In this Part of the Scheme for Construction Contracts

    "claim by the payee" means a written notice given by the party carrying out work under a construction contract to the other party specifying the amount of any payment or payments which he considers to be due and the basis on which it is, or they are calculated;

    "contract price" means the entire sum payable under the construction contract in respect of the work;

    "relevant construction contract" means any construction contract other than one - 

    (a) which specifies that the duration of the work is to be less than 45 days, or

    (b) in respect of which the parties agree that the duration of the work is estimated to be less than 45 days;

    "relevant period" means a period which is specified in, or is calculated by reference to the construction contract or where no such period is so specified or is so calculable, a period of 28 days;

    "value of work" means an amount determined in accordance with the construction contract under which the work is performed or where the contract contains no such provision, the cost of any work performed in accordance with that contract together with an amount equal to any overhead or profit included in the contract price;

    "work" means any of the work or services mentioned in section 104 of the Act.

top of page


The Contracts (Rights of Third Parties) Act 1999

The provisions of The Contracts (Rights of Third Parties) Act 1999 are as follows. © HMSO

Right of third party to enforce contractual term.     1. - (1) Subject to the provisions of this Act, a person who is not a party to a contract (a "third party") may in his own right enforce a term of the contract if-
 
 
    (a) the contract expressly provides that he may, or
 
    (b) subject to subsection (2), the term purports to confer a benefit on him.
      (2) Subsection (1)(b) does not apply if on a proper construction of the contract it appears that the parties did not intend the term to be enforceable by the third party.
 
      (3) The third party must be expressly identified in the contract by name, as a member of a class or as answering a particular description but need not be in existence when the contract is entered into.
 
      (4) This section does not confer a right on a third party to enforce a term of a contract otherwise than subject to and in accordance with any other relevant terms of the contract.
 
      (5) For the purpose of exercising his right to enforce a term of the contract, there shall be available to the third party any remedy that would have been available to him in an action for breach of contract if he had been a party to the contract (and the rules relating to damages, injunctions, specific performance and other relief shall apply accordingly).
 
      (6) Where a term of a contract excludes or limits liability in relation to any matter references in this Act to the third party enforcing the term shall be construed as references to his availing himself of the exclusion or limitation.
 
      (7) In this Act, in relation to a term of a contract which is enforceable by a third party-
 
 
    "the promisor" means the party to the contract against whom the term is enforceable by the third party, and
 
    "the promisee" means the party to the contract by whom the term is enforceable against the promisor.
Variation and rescission of contract.      2. - (1) Subject to the provisions of this section, where a third party has a right under section 1 to enforce a term of the contract, the parties to the contract may not, by agreement, rescind the contract, or vary it in such a way as to extinguish or alter his entitlement under that right, without his consent if-
 
 
    (a) the third party has communicated his assent to the term to the promisor,
 
    (b) the promisor is aware that the third party has relied on the term, or
 
    (c) the promisor can reasonably be expected to have foreseen that the third party would rely on the term and the third party has in fact relied on it.
      (2) The assent referred to in subsection (1)(a)-
 
 
    (a) may be by words or conduct, and
 
    (b) if sent to the promisor by post or other means, shall not be regarded as communicated to the promisor until received by him.
      (3) Subsection (1) is subject to any express term of the contract under which-
 
 
    (a) the parties to the contract may by agreement rescind or vary the contract without the consent of the third party, or
 
    (b) the consent of the third party is required in circumstances specified in the contract instead of those set out in subsection (1)(a) to (c).
      (4) Where the consent of a third party is required under subsection (1) or (3), the court or arbitral tribunal may, on the application of the parties to the contract, dispense with his consent if satisfied-
 
 
    (a) that his consent cannot be obtained because his whereabouts cannot reasonably be ascertained, or
 
    (b) that he is mentally incapable of giving his consent.
      (5) The court or arbitral tribunal may, on the application of the parties to a contract, dispense with any consent that may be required under subsection (1)(c) if satisfied that it cannot reasonably be ascertained whether or not the third party has in fact relied on the term.
 
      (6) If the court or arbitral tribunal dispenses with a third party's consent, it may impose such conditions as it thinks fit, including a condition requiring the payment of compensation to the third party.
 
      (7) The jurisdiction conferred on the court by subsections (4) to (6) is exercisable by both the High Court and a county court.
 
Defences etc. available to promisor.     3. - (1) Subsections (2) to (5) apply where, in reliance on section 1, proceedings for the enforcement of a term of a contract are brought by a third party.
 
      (2) The promisor shall have available to him by way of defence or set-off any matter that-
 
 
    (a) arises from or in connection with the contract and is relevant to the term, and
 
    (b) would have been available to him by way of defence or set-off if the proceedings had been brought by the promisee.
      (3) The promisor shall also have available to him by way of defence or set-off any matter if-
 
 
    (a) an express term of the contract provides for it to be available to him in proceedings brought by the third party, and
 
    (b) it would have been available to him by way of defence or set-off if the proceedings had been brought by the promisee.
      (4) The promisor shall also have available to him-
 
 
    (a) by way of defence or set-off any matter, and
 
    (b) by way of counterclaim any matter not arising from the contract,
  that would have been available to him by way of defence or set-off or, as the case may be, by way of counterclaim against the third party if the third party had been a party to the contract.
 
      (5) Subsections (2) and (4) are subject to any express term of the contract as to the matters that are not to be available to the promisor by way of defence, set-off or counterclaim.
 
      (6) Where in any proceedings brought against him a third party seeks in reliance on section 1 to enforce a term of a contract (including, in particular, a term purporting to exclude or limit liability), he may not do so if he could not have done so (whether by reason of any particular circumstances relating to him or otherwise) had he been a party to the contract.
 
Enforcement of contract by promisee.     4. Section 1 does not affect any right of the promisee to enforce any term of the contract.
 
Protection of promisor from double liability.     5. Where under section 1 a term of a contract is enforceable by a third party, and the promisee has recovered from the promisor a sum in respect of-
 
 
    (a) the third party's loss in respect of the term, or
 
    (b) the expense to the promisee of making good to the third party the default of the promisor,
  then, in any proceedings brought in reliance on that section by the third party, the court or arbitral tribunal shall reduce any award to the third party to such extent as it thinks appropriate to take account of the sum recovered by the promisee.
 
Exceptions.      6. - (1) Section 1 confers no rights on a third party in the case of a contract on a bill of exchange, promissory note or other negotiable instrument.
 
      (2) Section 1 confers no rights on a third party in the case of any contract binding on a company and its members under section 14 of the Companies Act 1985.
 
      (3) Section 1 confers no right on a third party to enforce-
 
 
    (a) any term of a contract of employment against an employee,
 
    (b) any term of a worker's contract against a worker (including a home worker), or
 
    (c) any term of a relevant contract against an agency worker.
      (4) In subsection (3)-
 
 
    (a) "contract of employment", "employee", "worker's contract", and "worker" have the meaning given by section 54 of the National Minimum Wage Act 1998,
 
    (b) "home worker" has the meaning given by section 35(2) of that Act,
 
    (c) "agency worker" has the same meaning as in section 34(1) of that Act, and
 
    (d) "relevant contract" means a contract entered into, in a case where section 34 of that Act applies, by the agency worker as respects work falling within subsection (1)(a) of that section.
      (5) Section 1 confers no rights on a third party in the case of-
 
 
    (a) a contract for the carriage of goods by sea, or
 
    (b) a contract for the carriage of goods by rail or road, or for the carriage of cargo by air, which is subject to the rules of the appropriate international transport convention,
  except that a third party may in reliance on that section avail himself of an exclusion or limitation of liability in such a contract.
 
      (6) In subsection (5) "contract for the carriage of goods by sea" means a contract of carriage-
 
 
    (a) contained in or evidenced by a bill of lading, sea waybill or a corresponding electronic transaction, or
 
    (b) under or for the purposes of which there is given an undertaking which is contained in a ship's delivery order or a corresponding electronic transaction.
      (7) For the purposes of subsection (6)-
 
 
    (a) "bill of lading", "sea waybill" and "ship's delivery order" have the same meaning as in the Carriage of Goods by Sea Act 1992, and
 
    (b) a corresponding electronic transaction is a transaction within section 1(5) of that Act which corresponds to the issue, indorsement, delivery or transfer of a bill of lading, sea waybill or ship's delivery order.
      (8) In subsection (5) "the appropriate international transport convention" means-
 
 
    (a) in relation to a contract for the carriage of goods by rail, the Convention which has the force of law in the United Kingdom under section 1 of the International Transport Conventions Act 1983,
 
    (b) in relation to a contract for the carriage of goods by road, the Convention which has the force of law in the United Kingdom under section 1 of the Carriage of Goods by Road Act 1965, and
 
    (c) in relation to a contract for the carriage of cargo by air-
 
      (i) the Convention which has the force of law in the United Kingdom under section 1 of the Carriage by Air Act 1961, or
 
      (ii) the Convention which has the force of law under section 1 of the Carriage by Air (Supplementary Provisions) Act 1962, or
 
      (iii) either of the amended Conventions set out in Part B of Schedule 2 or 3 to the Carriage by Air Acts (Application of Provisions) Order 1967.
Supplementary provisions relating to third party.      7. - (1) Section 1 does not affect any right or remedy of a third party that exists or is available apart from this Act.
 
      (2) Section 2(2) of the Unfair Contract Terms Act 1977 (restriction on exclusion etc. of liability for negligence) shall not apply where the negligence consists of the breach of an obligation arising from a term of a contract and the person seeking to enforce it is a third party acting in reliance on section 1.
 
      (3) In sections 5 and 8 of the Limitation Act 1980 the references to an action founded on a simple contract and an action upon a specialty shall respectively include references to an action brought in reliance on section 1 relating to a simple contract and an action brought in reliance on that section relating to a specialty.
 
      (4) A third party shall not, by virtue of section 1(5) or 3(4) or (6), be treated as a party to the contract for the purposes of any other Act (or any instrument made under any other Act).
 
Arbitration provisions.     8. - (1) Where-
 
 
    (a) a right under section 1 to enforce a term ("the substantive term") is subject to a term providing for the submission of disputes to arbitration ("the arbitration agreement"), and
 
    (b) the arbitration agreement is an agreement in writing for the purposes of Part I of the Arbitration Act 1996,
  the third party shall be treated for the purposes of that Act as a party to the arbitration agreement as regards disputes between himself and the promisor relating to the enforcement of the substantive term by the third party.
 
      (2) Where-
 
 
    (a) a third party has a right under section 1 to enforce a term providing for one or more descriptions of dispute between the third party and the promisor to be submitted to arbitration ("the arbitration agreement"),
 
    (b) the arbitration agreement is an agreement in writing for the purposes of Part I of the Arbitration Act 1996, and
 
    (c) the third party does not fall to be treated under subsection (1) as a party to the arbitration agreement,
  the third party shall, if he exercises the right, be treated for the purposes of that Act as a party to the arbitration agreement in relation to the matter with respect to which the right is exercised, and be treated as having been so immediately before the exercise of the right.
 
Northern Ireland.     9. - (1) In its application to Northern Ireland, this Act has effect with the modifications specified in subsections (2) and (3).
 
      (2) In section 6(2), for "section 14 of the Companies Act 1985" there is substituted "Article 25 of the Companies (Northern Ireland) Order 1986".
 
      (3) In section 7, for subsection (3) there is substituted-
 
 
    "(3) In Articles 4(a) and 15 of the Limitation (Northern Ireland) Order 1989, the references to an action founded on a simple contract and an action upon an instrument under seal shall respectively include references to an action brought in reliance on section 1 relating to a simple contract and an action brought in reliance on that section relating to a contract under seal.".
 
      (4) In the Law Reform (Husband and Wife) (Northern Ireland) Act 1964, the following provisions are hereby repealed-
 
 
    (a) section 5, and
 
    (b) in section 6, in subsection (1)(a), the words "in the case of section 4" and "and in the case of section 5 the contracting party" and, in subsection (3), the words "or section 5".
Short title, commencement and extent.     10. - (1) This Act may be cited as the Contracts (Rights of third Parties) Act 1999.
 
      (2) This Act comes into force on the day on which it is passed but, subject to subsection (3), does not apply in relation to a contract entered into before the end of the period of six months beginning with that day.
 
      (3) The restriction in subsection (2) does not apply in relation to a contract which-
 
 
    (a) is entered into on or after the day on which this Act is passed, and
 
    (b) expressly provides for the application of this Act.
      (4) This Act extends as follows-
 
 
    (a) section 9 extends to Northern Ireland only;
 
    (b) the remaining provisions extend to England and Wales and Northern Ireland only.

top of page


The Late Payment of Commercial Debts (Interest) Act 1998

The provisions of The Late Payment of Commercial Debts (Interest) Act 1998 are as follows. © HMSO

  PART I
  STATUTORY INTEREST ON QUALIFYING DEBTS
Statutory interest.     1. - (1) It is an implied term in a contract to which this Act applies that any qualifying debt created by the contract carries simple interest subject to and in accordance with this Part.
 
      (2) Interest carried under that implied term (in this Act referred to as "statutory interest") shall be treated, for the purposes of any rule of law or enactment (other than this Act) relating to interest on debts, in the same way as interest carried under an express contract term.
 
      (3) This Part has effect subject to Part II (which in certain circumstances permits contract terms to oust or vary the right to statutory interest that would otherwise be conferred by virtue of the term implied by subsection (1)).
 
Contracts to which Act applies.     2. - (1) This Act applies to a contract for the supply of goods or services where the purchaser and the supplier are each acting in the course of a business, other than an excepted contract.
 
      (2) In this Act "contract for the supply of goods or services" means-
 
 
    (a) a contract of sale of goods; or
 
    (b) a contract (other than a contract of sale of goods) by which a person does any, or any combination, of the things mentioned in subsection (3) for a consideration that is (or includes) a money consideration.
      (3) Those things are-
 
 
    (a) transferring or agreeing to transfer to another the property in goods;
 
    (b) bailing or agreeing to bail goods to another by way of hire or, in Scotland, hiring or agreeing to hire goods to another; and
 
    (c) agreeing to carry out a service.
      (4) For the avoidance of doubt a contract of service or apprenticeship is not a contract for the supply of goods or services.
 
      (5) The following are excepted contracts-
 
 
    (a) a consumer credit agreement;
 
    (b) a contract intended to operate by way of mortgage, pledge, charge or other security; and
 
    (c) a contract of a description specified in an order made by the Secretary of State.
      (6) An order under subsection (5)(c) may specify a description of contract by reference to any feature of the contract (including the parties).
 
      (7) In this section-
 
 
    "business" includes a profession and the activities of any government department or local or public authority;
 
    "consumer credit agreement" has the same meaning as in the Consumer Credit Act 1974;
 
    "contract of sale of goods" and "goods" have the same meaning as in the Sale of Goods Act 1979;
 
    "property in goods" means the general property in them and not merely a special property.
Qualifying debts.     3. - (1) A debt created by virtue of an obligation under a contract to which this Act applies to pay the whole or any part of the contract price is a "qualifying debt" for the purposes of this Act, unless (when created) the whole of the debt is prevented from carrying statutory interest by this section.
 
      (2) A debt does not carry statutory interest if or to the extent that it consists of a sum to which a right to interest or to charge interest applies by virtue of any enactment (other than section 1 of this Act).
 
  This subsection does not prevent a sum from carrying statutory interest by reason of the fact that a court, arbitrator or arbiter would, apart from this Act, have power to award interest on it.
      (3) A debt does not carry (and shall be treated as never having carried) statutory interest if or to the extent that a right to demand interest on it, which exists by virtue of any rule of law, is exercised.
 
      (4) A debt does not carry statutory interest if or to the extent that it is of a description specified in an order made by the Secretary of State.
 
      (5) Such an order may specify a description of debt by reference to any feature of the debt (including the parties or any other feature of the contract by which it is created).
 
Period for which statutory interest runs.     4. - (1) Statutory interest runs in relation to a qualifying debt in accordance with this section (unless section 5 applies).
 
      (2) Statutory interest starts to run on the day after the relevant day for the debt, at the rate prevailing under section 6 at the end of the relevant day.
 
      (3) Where the supplier and the purchaser agree a date for payment of the debt (that is, the day on which the debt is to be created by the contract), that is the relevant day unless the debt relates to an obligation to make an advance payment.
 
  A date so agreed may be a fixed one or may depend on the happening of an event or the failure of an event to happen.
      (4) Where the debt relates to an obligation to make an advance payment, the relevant day is the day on which the debt is treated by section 11 as having been created.
 
      (5) In any other case, the relevant day is the last day of the period of 30 days beginning with-
 
 
    (a) the day on which the obligation of the supplier to which the debt relates is performed; or
 
    (b) the day on which the purchaser has notice of the amount of the debt or (where that amount is unascertained) the sum which the supplier claims is the amount of the debt,
  whichever is the later.
 
      (6) Where the debt is created by virtue of an obligation to pay a sum due in respect of a period of hire of goods, subsection (5)(a) has effect as if it referred to the last day of that period.
 
      (7) Statutory interest ceases to run when the interest would cease to run if it were carried under an express contract term.
 
      (8) In this section "advance payment" has the same meaning as in section 11.
 
Remission of statutory interest.     5. - (1) This section applies where, by reason of any conduct of the supplier, the interests of justice require that statutory interest should be remitted in whole or part in respect of a period for which it would otherwise run in relation to a qualifying debt.
 
      (2) If the interests of justice require that the supplier should receive no statutory interest for a period, statutory interest shall not run for that period.
 
      (3) If the interests of justice require that the supplier should receive statutory interest at a reduced rate for a period, statutory interest shall run at such rate as meets the justice of the case for that period.
 
      (4) Remission of statutory interest under this section may be required-
 
 
    (a) by reason of conduct at any time (whether before or after the time at which the debt is created); and
 
    (b) for the whole period for which statutory interest would otherwise run or for one or more parts of that period.
      (5) In this section "conduct" includes any act or omission.
 
Rate of statutory interest.     6. - (1) The Secretary of State shall by order made with the consent of the Treasury set the rate of statutory interest by prescribing-
 
 
    (a) a formula for calculating the rate of statutory interest; or
 
    (b) the rate of statutory interest.
      (2) Before making such an order the Secretary of State shall, among other things, consider the extent to which it may be desirable to set the rate so as to-
 
 
    (a) protect suppliers whose financial position makes them particularly vulnerable if their qualifying debts are paid late; and
 
    (b) deter generally the late payment of qualifying debts.
  PART II
  CONTRACT TERMS RELATING TO LATE PAYMENT OF QUALIFYING DEBTS
Purpose of Part II.     7. - (1) This Part deals with the extent to which the parties to a contract to which this Act applies may by reference to contract terms oust or vary the right to statutory interest that would otherwise apply when a qualifying debt created by the contract (in this Part referred to as "the debt") is not paid.
 
      (2) This Part applies to contract terms agreed before the debt is created; after that time the parties are free to agree terms dealing with the debt.
 
      (3) This Part has effect without prejudice to any other ground which may affect the validity of a contract term.
 
Circumstances where statutory interest may be ousted or varied.     8. - (1) Any contract terms are void to the extent that they purport to exclude the right to statutory interest in relation to the debt, unless there is a substantial contractual remedy for late payment of the debt.
 
      (2) Where the parties agree a contractual remedy for late payment of the debt that is a substantial remedy, statutory interest is not carried by the debt (unless they agree otherwise).
 
      (3) The parties may not agree to vary the right to statutory interest in relation to the debt unless either the right to statutory interest as varied or the overall remedy for late payment of the debt is a substantial remedy.
 
      (4) Any contract terms are void to the extent that they purport to-
 
 
    (a) confer a contractual right to interest that is not a substantial remedy for late payment of the debt, or
 
    (b) vary the right to statutory interest so as to provide for a right to statutory interest that is not a substantial remedy for late payment of the debt,
  unless the overall remedy for late payment of the debt is a substantial remedy.
 
      (5) Subject to this section, the parties are free to agree contract terms which deal with the consequences of late payment of the debt.
 
Meaning of "substantial remedy".     9. - (1) A remedy for the late payment of the debt shall be regarded as a substantial remedy unless-
 
 
    (a) the remedy is insufficient either for the purpose of compensating the supplier for late payment or for deterring late payment; and
 
    (b) it would not be fair or reasonable to allow the remedy to be relied on to oust or (as the case may be) to vary the right to statutory interest that would otherwise apply in relation to the debt.
      (2) In determining whether a remedy is not a substantial remedy, regard shall be had to all the relevant circumstances at the time the terms in question are agreed.
 
      (3) In determining whether subsection (1)(b) applies, regard shall be had (without prejudice to the generality of subsection (2)) to the following matters-
 
 
    (a) the benefits of commercial certainty;
 
    (b) the strength of the bargaining positions of the parties relative to each other;
 
    (c) whether the term was imposed by one party to the detriment of the other (whether by the use of standard terms or otherwise); and
 
    (d) whether the supplier received an inducement to agree to the term.
Interpretation of Part II.     10. - (1) In this Part-
 
 
    "contract term" means a term of the contract creating the debt or any other contract term binding the parties (or either of them);
 
    "contractual remedy" means a contractual right to interest or any contractual remedy other than interest;
 
    "contractual right to interest" includes a reference to a contractual right to charge interest;
 
    "overall remedy", in relation to the late payment of the debt, means any combination of a contractual right to interest, a varied right to statutory interest or a contractual remedy other than interest;
 
    "substantial remedy" shall be construed in accordance with section 9.
      (2) In this Part a reference (however worded) to contract terms which vary the right to statutory interest is a reference to terms altering in any way the effect of Part I in relation to the debt (for example by postponing the time at which interest starts to run or by imposing conditions on the right to interest).
 
      (3) In this Part a reference to late payment of the debt is a reference to late payment of the sum due when the debt is created (excluding any part of that sum which is prevented from carrying statutory interest by section 3).
 

top of page